PMBOK® 8th Edition Interactive Calculation Suite
Reserve, Schedule & Resource Calculators
Simulate known-unknown contingency reserves vs management reserves (Page 192), evaluate Earned Value metrics (SPI/CPI), and analyze resource leveling schedule extensions.
1. Base Project Scope EstimateExcludes all reserves
2. Identified Known-Unknown Risks (Contingency Reserve)
EMV MethodWeather Ground Delay
Prob: 30% × Impact: $25,000
+$7,500
API Integration Rework
Prob: 40% × Impact: $15,000
+$6,000
Vendor Delivery Slip
Prob: 20% × Impact: $30,000
+$6,000
Add New Identified Risk:
3. Unknown-Unknown Reserve (Management Reserve %)
Requires CCB Approval5%
Budget Reserve Stack Analysis
Direct Scope Estimate:$500,000
+ Contingency Reserve (Known-Unknowns):$19,500
= COST BASELINE (PM Controlled):$519,500
+ Management Reserve (5% Unknown-Unknowns):$25,975
TOTAL PROJECT BUDGET:$545,475
PMBOK Page 192 Key Exam Distinction:
Earned Value performance metrics (EV, PV, AC) are measured strictly against the Cost Baseline ($519,500), NOT the total project budget!