The authoritative corrections issued for A Guide to the Project Management Body of Knowledge (PMBOK® Guide) — Eighth Edition (Second Printing). This hub applies every notable correction so the study material matches the corrected, authoritative text. Verify your print run via the numeral string ("10 9 8…") at the bottom of your copyright page.

5
Official Corrections
12
Corrected Definitions
3
Corrected Formulas
p. 40, 46, 157, 170, 185
Affected Pages

Each entry below is a notable correction from the official errata. The Issue describes what was wrong in the first printing; the Correction is the authoritative, corrected text.

p.40Figure

Plan Scope Management outputs

Guide portion — Figure 2-14

First Printing (Incorrect)

The Project management plan updates were missing the Quality management plan as a sub-bullet under the listed outputs.

Corrected (Second Printing)

"Quality management plan" was added as a sub-bullet to the Outputs listed under the Project management plan updates.

p.46Formula

Scope Creep & Requirements Stability equations

Guide portion — Table 2-6

First Printing (Incorrect)

The two equations in Table 2-6 had inverted variables, producing incorrect formulas.

Corrected (Second Printing)

Corrected equations: Scope Creep (%) = (Unplanned Deliverables / Total Deliverables) × 100, and Requirements Stability (%) = (Unchanged Requirements / Total Requirements) × 100. Scope Definition Accuracy (%) = (Planned Scope Items Correctly Delivered / Total Planned Scope Items) × 100.

p.185Definition

Start-to-finish (SF) dependency

Section 5 — Tools and Techniques

First Printing (Incorrect)

The Start-to-finish description had inverted explanations for successor and predecessor activities.

Corrected (Second Printing)

Start-to-finish (SF): a logical relationship in which a SUCCESSOR activity cannot finish until a PREDECESSOR activity has started. (The four PDM relationships are FS, FF, SS, and SF.)

p.157Definition

Contingent response strategies

Section 5 — Tools and Techniques

First Printing (Incorrect)

The original publication carried a duplicate description copied from "strategies for opportunities."

Corrected (Second Printing)

Contingent response strategies are risk strategies intentionally designed for implementation only if one or more specific trigger conditions occur. Examples: an audit response process activating only after an audit is requested, or planning to engage an alternate supplier only if and when the preferred supplier cannot perform against requirements. This lets the team avoid expending effort and resources against a risk until they are needed, shifting focus from the risk impact to the triggering event itself. Also called contingency plans or fallback plans.

p.170Removed Item

Estimation Technique description

Section 5 — Tools and Techniques

First Printing (Incorrect)

The Estimation Technique description listed "Relative Size Estimation" as a bullet, which has been removed.

Corrected (Second Printing)

The corrected list of the most common estimation techniques is: Expert judgment, Analogous estimating, Bottom-up estimating, Multipoint estimating, and Parametric estimating. ("Relative Size Estimation" was removed from this list.)